Installation is a sequence, not a task. Follow it and the machine is running on schedule; skip a step and the delay appears later, usually on opening day.

This is the on site routine we run with local crews, from the first foundation survey to the handover checklist.

ride assembly on site

Spesifikasi Utama

Barang Referensi
Step 1 Confirm foundations and anchor positions
Step 2 Assemble in the factory sequence
Step 3 Electrical connection and earthing
Step 4 Function and load commissioning
Step 5 Operator and maintenance training
Penyerahan Signed checklist and documentation set

Semua angka adalah nilai referensi dan dikonfirmasi dalam proposal teknik untuk situs Anda. Commissioning is the formal handover from installation to operation, and it ends with signed records. Melihat commissioning untuk latar belakang.

ride commissioning checks

Foundations and Assembly

The first job on site is not assembly, it is verification: foundations surveyed, anchor bolts checked against the drawing, and the base line confirmed. Assembly then follows the factory sequence, with torque values recorded and photographs taken at each stage so the factory can confirm progress remotely. Local labour usually carries out the work under a factory technician’s supervision.

Electrical Connection and Earthing

Electrical work follows the schematic supplied with the machine: supply, distribution, earthing and control wiring. Earthing is not optional in a tropical site with high rainfall, and every terminal is checked before power is applied for the first time. Cable routing is planned so that it can be inspected later without dismantling the ride.

Commissioning and Load Checks

Commissioning covers start and stop sequences, emergency stops, restraint locking, brake performance, travel limits and a full operating cycle. Where the design requires load testing, it is carried out and recorded before guests board. Penerangan, sound and any show programme are commissioned at the same time so the ride opens complete rather than finished later.

Training and Handover

Training happens on the machine: operators on start-up, loading, restraint checks and evacuation, and maintenance staff on the inspection routine, lubrication and wear parts. Handover ends with a signed checklist plus manuals, drawings, schematics and test records. Projects that follow this path – dari a park project to a single ride replacement – open on the date planned.


Opsi Tema dan Selesai

Buatlah sesuai dengan merek Anda: Installation model, supervision level and training scope.

Peralatan seperti ini diproduksi, beban diuji dan kontainer dimuat di kami 125,000 fasilitas meter persegi dengan cara yang sama produsen kendaraan, kemudian didukung dengan suku cadang dan saran teknis lama setelah commissioning. Pekerjaan proyek meliputi gambar tata letak, daftar peralatan dan dokumentasi bertahap dapat Anda serahkan langsung ke kontraktor lokal. The full timeline from order to opening, including freight and clearance, is set out in our amusement ride delivery and installation time.

Kirim rencana plot Anda, kisaran anggaran dan target tanggal pembukaan – kami akan mengembalikan proposal bertahap yang dapat Anda bawa langsung ke dewan Anda.