The container is the easy part. The month before it arrives decides whether installation takes five days or five weeks.

Installation delays are almost never caused by the equipment – they are caused by foundations that were not finished, power that was not connected or a crane that could not reach the site.

equipment foundation works

ข้อมูลจำเพาะที่สำคัญ

รายการ อ้างอิง
Civil works ฐานราก, slabs and anchor bolts
พลัง จัดหา, distribution board and earthing
Access Container route, crane position and laydown area
น้ำ Supply and drainage where required
เอกสาร Drawings, test reports and packing lists
Sequence Ready the site before the first container lands

ตัวเลขทั้งหมดเป็นค่าอ้างอิงและได้รับการยืนยันในข้อเสนอทางวิศวกรรมสำหรับไซต์ของคุณ.

installation on site

Start With the Drawings and a Site Survey

Before production ends, confirm the foundation drawings against the actual site: soil condition, water table, buried services and access routes. Mark the equipment positions on the ground and walk the delivery route with a tape measure, because the difference between a 45 และก 60 degree turn can decide whether a container truck reaches the gate. Any change agreed at this stage costs a drawing; the same change after arrival costs a crane and a week. If the layout is still open, ของเรา การออกแบบสวนสนุก service can settle ride positions before foundations are marked.

ฐานราก, Services and Surfaces

Foundations are the longest item on the critical path, so they should be poured and cured well before the ship berths. Anchor bolt positions must match the drawing exactly, and power must reach the ride’s control panel through an installed distribution board with proper earthing, not a temporary cable. If the ride needs water or drainage, complete those connections at the same time – trenching later under an installed ride is slow and expensive.

Delivery Day Logistics

Plan unloading as carefully as installation. Confirm the access road and gate widths, book the crane or forklift with the correct reach and capacity, and prepare a secure laydown area where crates can be stored in installation order rather than stacked at random. Keep the packing lists and drawings in one file on site, and check the crates against them on arrival so any shortage is reported within the insurance window.

การติดตั้ง, Commissioning and Training

Installation follows the manufacturer’s sequence and finishes with commissioning, load testing and operator training on the actual machines. Ask for the test records, the electrical schematics and a signed handover checklist, and store them where the maintenance team can find them. Rides that are commissioned properly – กับ crane lifts planned, torque values recorded and the control system proven under load – open on time and stay open.


การปรับแต่งการติดตั้ง

รายละเอียดต่อไปนี้ตรงกับสวนสาธารณะของคุณ: Site requirements, ภาพวาดรากฐาน, delivery planning and installation support.

เราอ้างเป็นโดยตรง ผู้ผลิตอุปกรณ์ จากก 125,000 ฐานการผลิต ตร.ม, ดังนั้นการสนทนาทางเทคนิคและการสนทนาเชิงพาณิชย์จึงเกิดขึ้นที่เดียวกัน, กับ 20 หลายปีของโครงการส่งออกที่อยู่เบื้องหลังคำตอบ. งานโครงการรวมถึงแบบร่าง, รายการอุปกรณ์และเอกสารแบบแบ่งเป็นระยะๆ คุณสามารถส่งตรงถึงผู้รับเหมาในพื้นที่ได้.

ให้รายละเอียดไซต์และกำหนดเวลาที่คุณกำลังทำงานให้เราทราบ – เราจะทำแผนที่เฟสต่างๆ, อุปกรณ์และโครงร่างต้นทุนเทียบกับมัน.