The container is the easy part. The month before it arrives decides whether installation takes five days or five weeks.

Installation delays are almost never caused by the equipment – they are caused by foundations that were not finished, power that was not connected or a crane that could not reach the site.

equipment foundation works

Specifiche chiave

Articolo Riferimento
Opere civili Fondazioni, solette e tirafondi
Energia Fornitura, quadro di distribuzione e messa a terra
Accesso Itinerario dei contenitori, posizione della gru e zona di deposito
Acqua Fornitura e drenaggio dove richiesto
Documentazione Disegni, rapporti di prova e liste di imballaggio
Sequence Ready the site before the first container lands

Tutti i valori sono valori di riferimento e sono confermati nella proposta ingegneristica per il vostro sito.

installation on site

Start With the Drawings and a Site Survey

Before production ends, confirm the foundation drawings against the actual site: soil condition, water table, buried services and access routes. Mark the equipment positions on the ground and walk the delivery route with a tape measure, because the difference between a 45 e un 60 degree turn can decide whether a container truck reaches the gate. Any change agreed at this stage costs a drawing; the same change after arrival costs a crane and a week. If the layout is still open, Nostro progettazione del parco divertimenti service can settle ride positions before foundations are marked.

Fondazioni, Services and Surfaces

Foundations are the longest item on the critical path, so they should be poured and cured well before the ship berths. Anchor bolt positions must match the drawing exactly, and power must reach the ride’s control panel through an installed distribution board with proper earthing, not a temporary cable. If the ride needs water or drainage, complete those connections at the same time – trenching later under an installed ride is slow and expensive.

Delivery Day Logistics

Plan unloading as carefully as installation. Confirm the access road and gate widths, book the crane or forklift with the correct reach and capacity, and prepare a secure laydown area where crates can be stored in installation order rather than stacked at random. Keep the packing lists and drawings in one file on site, and check the crates against them on arrival so any shortage is reported within the insurance window.

Installazione, Commissioning and Training

Installation follows the manufacturer’s sequence and finishes with commissioning, load testing and operator training on the actual machines. Ask for the test records, the electrical schematics and a signed handover checklist, and store them where the maintenance team can find them. Rides that are commissioned properly – con crane lifts planned, torque values recorded and the control system proven under load – open on time and stay open.


Personalizzazione dell'installazione

I seguenti dettagli sono abbinati al tuo parco: Site requirements, disegni di fondazione, delivery planning and installation support.

Citiamo come diretto produttore di apparecchiature da a 125,000 base produttiva mq, quindi la conversazione tecnica e quella commerciale avvengono nello stesso luogo, con 20 anni di progetti di esportazione dietro la risposta. Il lavoro del progetto include disegni di layout, elenchi e documentazione graduali delle attrezzature che puoi consegnare direttamente a un appaltatore locale.

Forniscici i dettagli del sito e la scadenza entro la quale stai lavorando – mapperemo le fasi, l'attrezzatura e il relativo costo.