The container is the easy part. The month before it arrives decides whether installation takes five days or five weeks.

Installation delays are almost never caused by the equipment – they are caused by foundations that were not finished, power that was not connected or a crane that could not reach the site.

equipment foundation works

Mga Pangunahing Detalye

item Sanggunian
Civil works Mga pundasyon, slabs and anchor bolts
Kapangyarihan Supply, distribution board and earthing
Access Container route, crane position and laydown area
Tubig Supply and drainage where required
Documentation Drawings, test reports and packing lists
Sequence Ready the site before the first container lands

Ang lahat ng mga numero ay mga halaga ng sanggunian at nakumpirma sa panukala sa engineering para sa iyong site.

installation on site

Start With the Drawings and a Site Survey

Before production ends, confirm the foundation drawings against the actual site: soil condition, water table, buried services and access routes. Mark the equipment positions on the ground and walk the delivery route with a tape measure, because the difference between a 45 at a 60 degree turn can decide whether a container truck reaches the gate. Any change agreed at this stage costs a drawing; the same change after arrival costs a crane and a week. If the layout is still open, aming Disenyo ng Amusement Park service can settle ride positions before foundations are marked.

Mga pundasyon, Services and Surfaces

Foundations are the longest item on the critical path, so they should be poured and cured well before the ship berths. Anchor bolt positions must match the drawing exactly, and power must reach the ride’s control panel through an installed distribution board with proper earthing, not a temporary cable. If the ride needs water or drainage, complete those connections at the same time – trenching later under an installed ride is slow and expensive.

Delivery Day Logistics

Plan unloading as carefully as installation. Confirm the access road and gate widths, book the crane or forklift with the correct reach and capacity, and prepare a secure laydown area where crates can be stored in installation order rather than stacked at random. Keep the packing lists and drawings in one file on site, and check the crates against them on arrival so any shortage is reported within the insurance window.

Pag-install, Commissioning and Training

Installation follows the manufacturer’s sequence and finishes with commissioning, load testing and operator training on the actual machines. Ask for the test records, the electrical schematics and a signed handover checklist, and store them where the maintenance team can find them. Rides that are commissioned properly – kasama crane lifts planned, torque values recorded and the control system proven under load – open on time and stay open.


Pagsasaayos ng Pag-install

Ang mga sumusunod na detalye ay tumugma sa iyong parke: Site requirements, mga guhit ng pundasyon, delivery planning and installation support.

Sinipi namin bilang direktang tagagawa ng kagamitan mula sa a 125,000 sqm production base, so the technical conversation and the commercial one happen in the same place, kasama 20 taon ng mga proyekto sa pag-export sa likod ng sagot. Kasama sa gawaing proyekto ang mga guhit ng layout, mga listahan ng mga phased na kagamitan at dokumentasyon na maaari mong ibigay diretso sa isang lokal na kontratista.

Ibigay sa amin ang mga detalye ng site at ang deadline kung saan ka nagtatrabaho – imamapa natin ang mga yugto, ang kagamitan at ang balangkas ng gastos laban dito.