Building a park where the infrastructure is still developing changes the priorities: power reliability, site preparation and phasing matter more than the attraction list.

This project delivered a park in phases, starting with attractions that could run on a stable power arrangement and adding more as the site matured.

park phase one equipment

Pagrindinės specifikacijos

Prekė Nuoroda
Šalis Nigeria
Projekto tipas New park build
Contract value USD 266,000 class project
Taikymo sritis Įranga, gabenimas, diegimo palaikymas
Challenge Power stability and site preparation
Approach Phase the build and open one zone at a time

Visi skaičiai yra pamatinės vertės ir yra patvirtinti jūsų svetainės inžineriniame pasiūlyme. Play equipment follows established playground practice with fall heights recorded on the layout. Žr Playground.

slide complex for park

Site and Infrastructure First

Before equipment was ordered, the site was reviewed for access, drenažas, water and power. Where the grid supply was uncertain, the design allowed for generator backup sized to the ride package, and power distribution was planned so that rides could be isolated rather than shutting the whole park.

Phasing the Attraction List

Phase one concentrated on attractions with predictable power demand and low maintenance: family rides, children equipment and play installations. Thrill rides were added in later phases once the park had trading data and a maintenance team in place – a sequence that reduces risk for a first-time operator.

Installation in a Remote Setting

Remoter sites demand more planning: crane availability, housing for the installation crew, and a secure laydown area for crates. Each shipment was timed so that installation crews and equipment arrived together, and local labour was trained during the build so maintenance knowledge stayed in the country.

Operating in a Developing Market

Pricing, staffing and spares were all planned around local conditions: simple ticket models, flexible opening hours and a spares kit that covers the fastest wearing components. Parks built this way follow the same principle behind our carnival ride package diapazonas – buy capacity you can operate reliably today, and expand with revenue.


Parinktys ir tematika

Viską, kas matoma, turite apibrėžti jūs: Ride mix, phasing, power arrangements and theming.

Kaip tiesioginis tiekėjas mes valdome visą grandinę: inžinerija, gamyba, gamyklos bandymai ir eksporto pakavimas vyksta a 125,000 kvadratinių metrų gamybinę bazę, o atsarginių dalių sąrašas pateikiamas po mašinos į jūsų svetainę. Projekto darbai apima maketavimo brėžinius, Laipsniškus įrangos sąrašus ir dokumentus galite perduoti tiesiai vietiniam rangovui.

Atsiųskite savo sklypo planą, biudžeto diapazonas ir tikslinė atidarymo data – grąžinsime laipsnišką pasiūlymą, kurį galėsite pateikti tiesiai į savo valdybą.