Almost every Indonesian enquiry begins with the same question, and the honest answer is that the number depends on five cost drivers – four of which are not the rides.

Here is how a park budget is actually built, and how to compare quotations so that the cheapest one does not become the most expensive project.

amusement ride shipping and crating

Wichtige Spezifikationen

Artikel Referenz
Cost drivers Ausrüstung, site works, Versand, Installation
Equipment share Usually the largest single line item
Civil works Stiftungen, Leistung, water and drainage
Versand Container volume plus port and inland charges
Phaseneinteilung Split the investment across seasons
Quotation basis Separated by scope, never one lump sum

Alle Angaben sind Richtwerte und werden im Planungsvorschlag für Ihren Standort bestätigt.

ride parts loaded in container

What Decides the Total Cost

The equipment list is only the first line. Foundations and slabs, power supply and distribution, water and drainage, access roads and fencing, shipping and port charges, installation labour and crane hire, then spares and training all sit on top. A park quoted without those lines is not cheaper – the costs simply move to a contractor you have not appointed yet.

Why Phasing Changes the Number

Phasing affects cost in two directions. Splitting the project reduces the peak capital requirement and lets early revenue fund later phases, but it can add shipping and mobilisation cost on the second delivery. The rule that works in practice is to phase by zone – opening one complete area rather than half of three – so guests see a finished park from day one. Unser park project process guide sets out where phasing decisions belong.

How to Compare Quotations

Ask for each quotation to separate equipment, Versand, installation support and spare parts, and to state what the buyer arranges locally. Check whether load test documents, drawings, operator training and a spares list are included, and confirm the currency, cost estimate validity period and payment terms. Two quotes that look similar on the total often differ substantially in what the buyer must pay locally.

What to Do Next

Send a plot plan, a target opening date and an indicative budget range. With those three pieces of information a supplier can propose a ride mix that fits the money instead of quoting a wish list, and can phase it so that the park opens on time with a complete experience.


Anpassen der Installation

Zu den standortspezifischen Auswahlmöglichkeiten gehören:: Quotation scope, phasing and delivery terms.

Das gleiche Fabrik für Unterhaltungsgeräte Das baut die Fahrt auf und transportiert sie auch, dokumentiert es und unterstützt es – 125,000 qm Produktionsfläche und ein Dokumentationspaket, das lokale Inspektoren nutzen können. Die Projektarbeit umfasst Layoutzeichnungen, Gestaffelte Ausrüstungslisten und Dokumentationen, die Sie direkt an einen örtlichen Auftragnehmer weitergeben können.

Teilen Sie uns die Standortdetails und den Termin mit, an dem Sie arbeiten – Wir werden die Phasen kartieren, die Ausstattung und die Kostenaufstellung dazu.